Project specifications

 

Order:   Hotel Via Senato 5 – Milano
Client:   Co.ge.fa spa
Place:   Milano
Completion date:   2025

 

 

project details

 

Order:   Baglioni Hotel
Client:   REALE MUTUA ASSICURAZIONI
Place:   Via Senato - Milano
Year:   2002
   

Air conditioning - water and sanitary system - fire hydrants

Nr. 38 Suite

 

project details

 

Order:   San Biagio Hotel
Client:   COOPSETTE SOC. COOP.
Place:   Bolzaneto (GE)
Year:   2003
    Air conditioning - water and sanitary system - fire hydrants
Total area mq 7,900

project details

 

Order:   Albergo Hotel NH S.Stefano
Client:   DEGA
Place:   Torino
Year:   2005
   

Air conditioning - water and sanitary system - fire hydrants

Total area mq 5,700

project details

 

Order:   Albergo Hotel Domina
Client:   IMPRESA MARCORA
Place:   Novate (Mi)
Year:   2007
   

Air conditioning - water and sanitary system - fire hydrants and sprinklers

Total area mq 8,600 and car parking mq 3,600

project details

 

Order:   Hotel BENTLEY (5 stelle)
Client:   COOPSETTE SOC.COOP.
Place:   Genova
Year:   2007
   

Air conditioning - water and sanitary system - fire hydrants

Total area mq 4,800

Total treated air mc/h 52,000

Total cooling power kw 570v

Total thermal power kw 720

 

project details

 

Order:   Novotel Hotel
Client:   ITALCANTIERI
Place:   Cardano al Campo (Va)
Year:   2007
   

Air conditioning - water and sanitary system - fire hydrants and sprinklers

Nr. 208 Hotel rooms

Total treated air mc/h 78,000

Total cooling power kw 840

Total thermal power kw 780

Covered car parking mq 7,000

project details

 

Order:   NH Hotel, Fiera Milano
Client:   C.M.B.
Place:   Rho-Pero (Mi)
Year:   2008
   

Air conditioning - water and sanitary system - fire protection

Total area mq 23,388

Nr. 398 Hotel rooms

Total cooling power kw 1,804

Total thermal power kw 3,966

Total treated air mc/h 139,100

project details

 

Order:   Albergo Hotel Holiday Inn       
Client:   COOPERATIVA CESI
Place:   Roma
Year:   2009
   

Air conditioning - water and sanitary system - fire hydrants and sprinklers

Nr. 300 Hotel rooms

Total treated air mc / h 112,000

Total cooling power kw 1,200

Total thermal power kw 1,340

 

project details

 

Order:   Centro Turistico Ricettivo Vicarello
Client:   COOPSETTE SOC.COOP.
Place:   Volterra (Pi)
Year:   2010
   

Air conditioning, water and sanitary system and fire hydrants

Central hotel building and secondary buildings

two cooling groups power kw 1,160

 

project details

 

Order:   Albergo Hotel Best Western Premier Chc Airport
Client:   COOPSETTE SOC.COOP.
Place:   Sestri Ponente (Ge)
Year:   2012
     

The building stands in the historical center of Turin, in the block of San Bartolomeo in Piazza Carlo Emanuele II. The building renovation works will allow the change of use destination from residential to hospitality. The gross floor area of the building is approximately 10,800 square metres, plus service areas and an underground car park that will develop under the courtyard. On the ground floor and basement are provided the main hotel services such as reception, bar, restaurant, conference facilities, shops facing the commercial Via Maria Vittoria. The system is made with cooled heat pumps with well water and recovery for domestic hot water.

 

 

DETAILS OF THE PROJECT

 

Order:   Hotel Carlina P.zza Carlo Emanuele
Client:   CARLINA Srl
Place:   Torino
Completion date:   In progress

 

photo gallery